This critique of the Eko Atlantic City environmental impact assessment, EIA has been the results of a week spent reading a library copy of the submission by the South Energyx Nigeria Limited, SENL to the Federal Ministry of Environment in Abuja. It is not aimed at arguing the credibility of scientific technicalities or at pursuing their verification as presented. The focus is rather on the project logic, the rationale, potential for impacts, the risk factor and the possibility as well as the capability to mitigate unavoidable consequences, but also to identify the necessity to situate a precautionary principle on what the project must not do. The analytical approach in this manuscript is however not devoid of scientific knowledge that complements information on governance and the socio-economic status of Nigeria.
This critique of the Eko Atlantic City environmental impact assessment, EIA has been the results of a week spent reading a library copy of the submission by the South Energyx Nigeria Limited, SENL to the Federal Ministry of Environment in Abuja. It is not aimed at arguing the credibility of scientific technicalities or at pursuing their verification as presented. The focus is rather on the project logic, the rationale, potential for impacts, the risk factor and the possibility as well as the capability to mitigate unavoidable consequences, but also to identify the necessity to situate a precautionary principle on what the project must not do. The analytical approach in this manuscript is however not devoid of scientific knowledge that complements information on governance and the socio-economic status of Nigeria.
·
·
Thus, the analysis of the EIA is not
so much over claims by the proponents to protect the shoreline from erosion and
drive economic development in Lagos at the conclusion of their activities, but
more about the eventual and longer term impacts of constructing a city on
reclaimed land from coastal marine sediments.
The indirect
effects of developments are often an order of magnitude higher than the direct
effects assessed by environmental impact assessments. The construction of a new city on reclaimed
and compacted marine sediments within a critical ecological system raises
justifiable public concern over potential impacts, the clarity of the EIA
process and the scientific credibility of its contents. It is for these reasons
that the Eko Atlantic City project has generated current controversy and
extensive debate.
·
·
The EIA is
honest when it states that ‘public opinion’ is a risk factor. That a proposed
project is queried by a concerned community or by concerned individuals is
nothing new all over the world. It is difficult not to believe that the
attitude of SENL and the Lagos State Government in not engaging with community
members over the contents of the Eko Atlantic City EIA has not been deliberate
in order to avoid the ‘Niger delta syndrome’ of communities making incessant financial
demands for hosting projects.
·
·
Whichever way
it is viewed, while it may be possible to hide the impact assessment of
processes leading to the construction of a new city in the Eti-Osa Local
Government Area of Lagos State, the activities on the ground will be obvious as
they progress. That is when community agitation could emerge and grow into
militancy and armed conflict. The genesis of the conflict in the Niger delta
goes back to an unchanging and undemocratic governance culture in Nigeria that is
anxious to propel development on the direction of a few ‘Captains of Industry,’
less on the views of the majority in the surrounding community.
·
·
For these and
other reasons it is necessary for communities in Lagos that may feel impacted
by the proposed project to avail themselves of legal advice on how to invoke
the Freedom of Information Act (FoI) which affords unhindered access to
information at the disposal of government and its agencies. It is impossible
for millions of Nigerians, if they were interested to make their comments on a
single EIA over 300 pages long, displayed in hard copy on a library table,
without a website reference within a month. The EIA Unit of the Federal
Ministry of Environment must find a better way of divulging information to the
public or be constrained by law to do so.
·
·
EIAs have often
been criticized for having too narrow spatial and temporal scope. At present no
procedure has been specified for determining a system boundary for the
assessment. The system boundary refers to ‘the spatial and temporal boundary of
the proposal’s effects’. This boundary is determined by the applicant and the
lead assessor, but in practice, almost all EIAs address the direct, on-site
effects alone.[4]The EIA of Eko Atlantic City is not an exception in
many ways.
·
·
Many of the
environment impact properties cannot be measured on a scale e.g. landscape
quality, lifestyle quality, social acceptance etc. and moreover these
indicators are very subjective. EIAs began to be used in the 1960s as part of a
rational decision making process. It involved a technical evaluation that would
lead to objective decision making. EIA was made legislation in the US in the
National Environmental Policy Act (NEPA) 1969. It has since evolved as it has
been used increasingly in many countries around the world. As per Jay et al.(2006),
EIA as it is practiced today, is being used as a decision aiding tool rather
than decision making tool. There is growing dissent on the use of EIA as its
influence on development decisions is limited and there is a view it is falling
short of its full potential.
·
·
The projected
benefits of this project over which there has been much publicity, must be
superimposed over the costs, risks and potential detrimental impacts around
which there is silence. Perhaps it is traditional business practice to take
risks. But where such risks are to human lives, extreme caution has to be
exercised, and the people at risk, whether they be rich or poor, property
owners or the homeless and landless must be allowed a voice in the
decision-making process.
·
·
The public will
be advised to watch out for the subsequent impact assessments on further phases
of the project, while demanding for intensified debate on what has been
submitted to date. Ideally an EIA must be followed by an audit. These audits
serve the purpose to compare actual impacts to those that were
predicted. Audits are the responsibility
of NESREA, the National Environmental Standards and Regulations Enforcement
Agency, a separate organization/parastatal within the Ministry of Environment.
NESREA is hardly 4 years in existence and is overstretched in attempts to audit
businesses nationwide.
·
·
In all of this,
a problem is that many communities in Nigeria and their members are unaware of
the existence of an EIA process, and even if they did, often lack the literacy
and numeracy to know what to do with it. They must be empowered through
capacity education programmes to take their destiny in their own hands.
·
·
It is important
to find a solution to beach loss at the Lagos Bar beach and be prepared for sea
level rise. The strategic option of sea defences is not new. Surprisingly the
EIA does not cite ‘success stories’ and comparative case studies from countries
around the globe that Lagosians could use as a reference base. People are
anxious to know where a similar project in a developing tropical country has
been successfully executed.
·
·
The Government
of Lagos is in a hurry and has instructed SENL to complete the EIA for Phase 2
as soon as possible. What needs to be done is to convene a workshop of the
stakeholders and interested groups and experts to come up with a written
reaction to the entire Eko Atlantic City project, based on expert advice from
within the country, and possibly from overseas. Opinions may differ, but it is
always beneficial to understand why people are motivated to make decisions in a
particular direction.
I want to thank you for this Post. I am an MSc student of Development Planning and Research from the University of Reading, UK. I have been following this project for some time now, my interest was to know the level of community engagement and involvement in the entire project, i.e. from conception to implementation unfortunately non as in the case of Okum Afla community. I flew to Nigeria in July and went straight to Alfa Beach spent some day in the community, me had a focus group meeting with the chiefs and the traditional leader but to my amazement this community has been completely neglected. I carried out field research met with community members, and most of them are not even aware of such project but all they can say was how their shore has been depleted by the ocean surge which intensified about two years ago washing up even building and other social amenities. Why are Nigerian leaders so insensitive to the plight of local people, Gov. Fashola is a lawyer, he should know this things. My research is still on, My prayer is that the Niger Delta case will not repeat itself here
ReplyDeleteHi Leenk technologies, my name is francis and I am a journalist working presently on the EAC Project and would like to ask you a few questions based on your research. If you can please reach me on enyiel@yahoo.com
ReplyDelete